Rusina Mining Provides Acoje Nickel Direct Ship Update
Friday September 28, 2007, 11:00 am

Original Announcement: Acoje Nickel Direct Ship Update

Rusina Mining provided ongoing construction progress for the first nickel laterite ore shipments from its Acoje project in the Philippines, with local partner DMCI reporting that the main pier at the Santa Cruz export port will be ready next month. This is despite interruptions caused by the current extended monsoonal conditions being experienced across South East Asia. DMCI Holdings Inc is currently completing the pier's compacted graded fill, concrete interlocking vertical fending and reinforced concrete sea mats that will form a permanent sloping loading ramp for the ship side loading barges.