Origin Energy Announces Contact Energy New Plymouth Power Station Outage
Wednesday October 24, 2007, 9:30 am

Original Announcement: Contact Energy New Plymouth power station outage

Origin Energy announced that the outage to manage asbestos at Contact Energy's New Plymouth power station will see the plant closed for at least six months. A month ago asbestos was discovered under insulation pipe lagging in the plant's turbine hall and boiler room and the plant was closed to investigate removal options. The power station as maintained for many years an asbestos register which recorded where asbestos was known to be located. Procedures are in place to safely manage this asbestos.

More information about ORG.AX

  •   