Catalpa Resources Reports Edna May Gold Project on Schedule Thursday September 10, 2009, 11:41 am Original Announcement: Edna May Gold Project on Schedule Catalpa Resources provided a market update on construction progress at its flagship Edna May Gold Project, at Westonia in WA, reporting the company has commissioned an 88-room village including kitchen and dining facilities in the town of Westonia in early August. The village is designed to serve as the permanent accommodation for normal operations post commissioning of the mine. Process plant civil earthworks are also almost complete. The majority of the plant site earthworks including crusher dump pocket, crushed ore stockpile, grinding, leach and absorption, and gold recovery area are now complete and construction has commenced on the raw and process water dams. The project remains within budget, and is on schedule to commence first gold production in mid 2010.More information about CAH.AX |
![]() |
|
|
![]() |