Rusina Mining Provides Heap Leach Trial Update
Friday September 25, 2009, 12:36 pm

Original Announcement: Heap Leach Trial Update

Rusina Mining reported the heap leach pad and pilot plant is now complete. The rolls crusher transferred from JV partner European Nickels Caldag operation in Turkey has now arrived on site and is in the process of being constructed. Once the crusher has been erected and commissioned approx. 3,000t of laterite ore will be crushed, agglomerated and stacked on the trial leach pad. The irrigation pipes will be placed and a HDPE raincoat will cover both the pad and the ponds. Leaching is expected to commence shortly before Christmas.