Well Well Type Spud Date Finish Date
--------------------------------------------------
Tilbrook#9a Exploration 16 Oct 2009 5 Nov 2009
--------------------------------------------------
Well Current Status
--------------------------------------------------
Tilbrook#9a Drilled to 506m, logged, cased and 2 DST's
complete. Suspended as future producer.
==================================================
--------------------------------------------------
Well Well Type Spud Date Finish Date
--------------------------------------------------
Tilbrook#9 Exploration 8 Nov 2009 20 Nov 2009
vertical (Planned) (Planned)
--------------------------------------------------
Well Current Status
--------------------------------------------------
Tilbrook#9 Preparing to drill then shutdown for
vertical a planned crew break.
==================================================
--------------------------------------------------
Well Well Type Spud Date Finish Date
--------------------------------------------------
Tilbrook#10b Exploration 22 Nov 2009 4 Dec 2009
(Planned) (Planned)
--------------------------------------------------
Well Current Status
--------------------------------------------------
Tilbrook#10b Site preparation completed.
==================================================
--------------------------------------------------
Well Well Type Spud Date Finish Date
--------------------------------------------------
Tilbrook#10a Exploration 6 Dec 2009 12 Dec 2009
(Planned) (Planned)
--------------------------------------------------
Well Current Status
--------------------------------------------------
Tilbrook#10a Site preparation in progress.
==================================================
Boart Longyear is the drilling contractor.
Summary : Seismic program
-----------------------------------------------------------------
Area Type Start Finish Date Current Status
-----------------------------------------------------------------
Mt St Martin 5 km of 19 Oct 2009 21 Oct 2009 Completed.
(ATP 688P) Vibroseis Data processing
Tilbrook 5 km of 22 Oct 2009 23 Oct 2009 Completed.
(ATP 688P) Vibroseis Data processing
Paranui 10 km of 3 Nov 2009 4 Nov 2009 Acquisition
(ATP 769P) dynamite completed.
seismic
=================================================================
Expected operations in the next weekWestSide Corporation Ltd Angus Karoll Chairman and CEO TEL: +61-7-3020-0900