Catalpa Resources Reports 7 Months from First Gold Pour at Edna May Operations Thursday November 19, 2009, 8:21 am Original Announcement: Edna May Operations - 7 months from first gold Catalpa Resources reported on construction progress at its Edna May Gold Project at Westonia, WA, confirming the project is within budget, and on schedule to pour first gold in seven months time (June 2010). A number of significant project milestones have been reached in recent weeks as the Project progresses rapidly through the construction phase towards commissioning. The finalisation of an equipment hire and maintenance contract with Force Equipment Hire and Service on 22 October 2009 is a major milestone, enabling the commencement of 24 hour mining operations. The mining works to date have focused on the establishment of road access to the tailing storage facilities, mill ROM pad access ramp and the removal of a waste stockpile surrounding the pit area.More information about CAH.AX |
![]() |
|
|
![]() |